| Project
Costs and Funding |
|
Project Cost |
| Phase 1 improvements |
$950,600 |
| Total Project Costs for all Phases |
$4,600,000 |
|
Funding |
| City of Flint for Phase 1 |
$250,000 |
| Clean
Michigan Initiative (CMI) Recreation Bond Grant (for 1999) |
$700,600 |
| Total Investment so far |
$950,600 |
|